Due to problems discovered by TELEHOUSE with the electric distribution
switch during the migration of another UPS, the work on our UPS has been
postponed while this matter is investigated. We will notify you in advance
when the new install date is set.

David

--
|> /+\ \| | |>

David Croft
IT - Network Operations
Sargasso Networks

---------- Forwarded message ----------
Date: Sat, 6 Jan 2007 03:37:28 -0500 (EST)
From: David Croft <david at sargasso.net>
To: David Croft <david at sargasso.net>
Subject: [Sargasso Announce] Advance notification of UPS upgrade work (update)

Please note that the end date listed in my previous e-mail is incorrect. This
is due to the fact that this maintenance was originally scheduled a week
earlier.

Correct schedule:

Start: Saturday, January 20th 2007  4pm (EST)
End:   Sunday, January 21st 2007    12 noon (EST)

Regards,

David

--
|> /+\ \| | |>

David Croft
IT - Network Operations
Sargasso Networks

---------- Forwarded message ----------
Date: Fri, 5 Jan 2007 14:22:27 -0500 (EST)
From: David Croft <david at sargasso.net>
Reply-To: support at sargasso.net
To: David Croft <david at sargasso.net>
Subject: [Sargasso Announce] Advance notification of UPS upgrade work

TELEHOUSE have notified us that they will be performing UPS upgrades on our
power supply on January 20th. Pre-testing of the equipment has already taken
place to aid in a smooth transition.

Although there is no downtime anticipated as a result of this work, the UPS
system will be out of operation during this time and we will be running on
utility power. Therefore, in the unlikely event of a utility outage, there will
be an outage while the generators are engaged.

Please see below for further technical information:

Start Date: Saturday, January 20, 2007; 04:00 PM (EST)
End Date: Sunday, January 14, 2007; 12:00 noon (EST)

Summary of Work: Migrating existing UPS#1 and #2 to parallel configuration.

Impact: Customers fed from UPS#1 or #2 should note that your power feed during
this period comes only from the electric utility serving 25 Broadway
("utility"). When isolating/getting the UPS back on line, TELEHOUSE foresees
continuous service.

Potential Risk: Just in case of a utility power failure during this work, a 5
minute to 15 minute power outage would happen, while TELEHOUSE restores power
by manually switching to a 25B generator feed.

TELEHOUSE expects that each weekend's work and various tests will require
twenty (20) hours. However, the test results might necessitate an extension of
our timeframe by two to three hours.